TK1116 : Cost-baxsed Planning of Gas Distributed Generation Resources to Mitigate Power Losses in Radial Distribution Grids
Thesis > Central Library of Shahrood University > Electrical Engineering > MSc > 2026
Authors:
[Author], Mojtaba Shivaie[Supervisor]
Abstarct: Abstract Load growth in radial distribution grids increases feeder currents, power losses, voltage drops, and equipment loading. Conventional reinforcement through new feeders, conductor upgrades, and substation expansion often requires high capital investment and long implementation periods. Gas-fired distributed generation (DG) can provide a flexible alternative because of its dispatchability, proximity to load centers, and potential for combined heat and power production. However, its effectiveness strongly depends on installation timing and location. This thesis presents a cost-baxsed planning frxamework for determining the optimal timing and location of fixed-capacity gas-fired DG units in a radial distribution grid. The economic model includes installation and maintenance costs, power-loss costs, electricity purchase costs, and revenues from electricity and heat sales. Bus-voltage limits and feeder thermal capacities are considered as the main technical constraints. Load demand is assumed to grow at a constant annual rate, and the annual load-duration curve is represented by peak, medium, and baxse-load levels. A forward dynamic heuristic is used to solve the multi-year planning problem. The network is evaluated sequentially over the planning horizon, and whenever a voltage or thermal constraint is violated, candidate DG installation strategies are examined. Infeasible alternatives are removed, while a predefined number of superior paths is retained for subsequent years. The final plan is selected baxsed on the maximum accumulated profit over the planning horizon. The proposed method is applied to a 20-kV radial distribution system with 24 buses, 23 branches, and 23 loads over a 20-year horizon. A 3% annual load-growth rate, ten retained planning paths, and 200-kVA gas-fired DG units are considered. Results show that the first reinforcement is required in year 7, with the first DG unit installed at bus 4. By the end of the planning horizon, ten units with a total capacity of 2000 kVA are installed. After year 10, the annual loss cost decreases despite continued load growth, while electricity purchase costs remain relatively stable. The accumulated profit over the 20-year period reaches EUR 10.0250 million, excluding additional benefits from deferred feeder and substation expansion. The results indicate that staged gas-fired DG planning can reduce loss and electricity-purchase costs, maintain network technical feasibility, and defer conventional reinforcement. Future work may consider uncertainty, gas-network constraints, emissions, protection requirements, project lead times, and part-load operation.
Keywords:
#_Cost-baxsed planning #DG placement #Distribution Grid #forward dynamic method #Gas-fired distributed generation #Installation Timing #Power-Loss Reduction #Radial_ Keeping place: Central Library of Shahrood University
Visitor: